| Karnataka State - PPP Projects & their Status as on May 30, 2010 ( Report re-produced based on data from KUM) | ||||||||||
| Sl.No. | Major Sector | Project Name | Sponsor Dept | Exec. Agency | Estimated cost(Rs.in Crores) | Modality (BOOT/BOT) | Likely Date of Completion | Current Status/ Remarks if any | ||
| 1 | Energy | B | A | 700 MW Gas based power project - I: Davangere | PCKL | 2800 | BOO | RFQ to be issued on 04/06/10 | ||
| 2 | Energy | B | A | 700 MW Gas based power project - II: Belgaum | PCKL | 2800 | BOO | RFQ to be issued on 04/06/10 | ||
| 3 | Energy | B | A | 700 MW Gas based power project - III : Gadag | PCKL | 2800 | BOO | RFQ to be issued on 04/06/10 | ||
| 4 | Energy | City Gas Distribution in karnataka | GAIL | GAIL & KSIIDC Joint Venture to undertake on PPP mode | ||||||
| 5 | Industrial Infrastructure | D | A | Devanahalli Business Park (DBP) | KSIIDC | KIPDC | 9000.00 | DBOT | RFQ by end June 2010 | |
| 6 | Industrial Infrastructure | Development of VADA in Bellary | Infrastructure Development Department | VADA | 30000.00 | Pre-feasibility Study completed. RFQ by June/July 2010; to be taken up in phases | ||||
| 7 | Industrial Infrastructure | Development of Steel Ancillary Park at Bellary | Commerce & Industries | KIADB | 146.00 | RFQ process on | ||||
| 8 | Industrial Infrastructure | Development of Engineering Park at Holalkere, Chitradurga | Commerce & Industries | KIADB | 46.00 | RFQ process on | ||||
| 9 | Industrial Infrastructure | Development of Engineering Park at Sira, Tumkur | Commerce & Industries | KIADB | 156.00 | RFQ process on | ||||
| 10 | Industrial Infrastructure | Development of Integrated Industrial Township at Dharwad | Commerce & Industries | KIADB | 395.00 | RFQ process on | ||||
| 11 | Industrial Infrastructure | Deveopment of Defence Manufacturing Hub at Challakere, Chitradurga | Commerce & Industries | KIADB | 110.00 | RFQ process on | ||||
| 12 | Industrial Infrastructure | Development of Multi-Product SEZ at Bagewadi, Bijapur | Commerce & Industries | KIADB | 666.00 | RFQ process on | ||||
| 13 | Industrial Infrastructure | Development of Textile SEZ at Doddaballapur, Bangalore | Commerce & Industries | KIADB | 190.00 | RFQ process on | ||||
| 14 | Industrial Infrastructure | D | A | Setting up of sector specific Special Economic Zone for Biotechnology sector at Electronic city , Phase - III, Bangalore | IT , BT ,S&T | KBITS | 522.00 | BOT | 4 years from the date of award | Bid process to be initiated |
| Note: | IDD - | IDD | Infrastructure Development Department | |||||||
| PWD | PWD | Public Works Department | ||||||||
| KSIIDC | KSIIDC | Karnataka State Industrial Investment & Development Corporation | ||||||||
| BARL | Bangalore Airport Rail Link Limited | |||||||||
| KSHIP | Karnataka State Highway Improvement Project | |||||||||
| VADA | Vijayanagar Area Development Authority | |||||||||
| KIPDC | KSIIDC & IL&FS Project Development Company | |||||||||
| KSRTC | Karnataka State Road Transport Corporation | |||||||||
| NWKRTC | North-West Karnataka Road Transport Corporation | |||||||||
| NEKRTC | North-East Karnataka Road Transport Corporation | |||||||||
| NHAI | National Highway Authority of India | |||||||||
| BUDA | Belgaum Urban Development Authority | |||||||||
| iDeCK | infrastructure Development Corporation (Karnataka) Limited | |||||||||
| BDA | Bangalore Development Authority | |||||||||
| KRDCL | Karnataka Road Development Corporation Limited | |||||||||
| PCKL | Power Corporation Karnataka Limited | |||||||||
| DMA | Directorate of Municipal Administration | |||||||||
| MCC | Mysore City Corporation | |||||||||
| GAIL | Gas Authority of India Limited | |||||||||
| KIADB | Karnataka Industrial Area Development Board | |||||||||
| BMTC | Bangalore Metropolitan Transport Corporation | |||||||||
| KBITS | Karnataka Biotechnology and Information Technology Services | |||||||||
| IT, BT, S&T | Information Technology, Bio-technology, Science&Technology Department | |||||||||