| Karnataka State - PPP Projects & their Status as on May 30, 2010 ( Report re-produced based on data from KUM) | ||||||||||
| Sl.No. | Major Sector | Project Name | Sponsor Dept | Exec. Agency | Estimated cost(Rs.in Crores) | Modality (BOOT/BOT) | Likely Date of Completion | Current Status/ Remarks if any | ||
| 1 | Transport & Logistics | Monorail Project in Bangalore (40 km) | IDD | BARL | 5600.00 | BOT | DPR under process | |||
| 2 | Transport & Logistics | Monorail Project in Bangalore - Swiss Challenge (15 km) | IDD | BARL | 2100.00 | BOT | DPR under Preparation | |||
| 3 | Transport & Logistics | Development of modern sea port at Haldipur in the coast line of Karnataka (Swiss Challenge ) | PWD/IDD | IDD/PWD | 1900 | BOOT | DPR under preparation. | |||
| 4 | Transport & Logistics | F | C | Development of Port at Tadadi - 34 MMT - Phase - I | IDD | KSIIDC | 3000 | BOT | 1. RFP for Technical consultants. | |
| 2. RFQ for developer issued; Pre-bid on 5th Jun '10 | ||||||||||
| 5 | Transport & Logistics | Development of SH 132 connecting Bellary to Andhra Pradesh | IDD | KSHIP | 169.33 | DBOT | Tender called for Annuity based bidding | |||
| 6 | Transport & Logistics | Development of Logistic Park in Bangalore | IDD | KSIIDC | 110.00 | Feasibility Study done | ||||
| 7 | Transport & Logistics | Development of ITH in Mysore Road, Bangalore | KSRTC | KIPDC | 75.00 | Pre-feasibility study done | ||||
| 8 | Transport & Logistics | Development of ITH in Peenya in Bangalore | KSRTC | KIPDC | 275.00 | Pre-feasibility study done | ||||
| 9 | Transport & Logistics | Development of ITH in Yelahanka, Bangalore | KSRTC | KIPDC | 275.00 | Pre-feasibility study done | ||||
| 10 | Transport & Logistics | Development of ITH in Yeshwanthpura, Bangalore | KSRTC | KIPDC | 75.00 | Pre-feasibility study done | ||||
| 11 | Transport & Logistics | Hubli- Ankola Railway Line | Infrastructure Development Department | Railways with Govt. of Karnataka Participation | 1200.00 | Waiting for Environmental clearance | ||||
| 12 | Transport & Logistics | Talaguppa - Honnavar Railway Line | Infrastructure Development Department | Railways with Govt. of Karnataka Participation | 997.00 | Announced in central Budget; Feasiibility Report done; Awaiting Railway Ministry's clearance for PPP procurement | ||||
| 13 | Transport & Logistics | Bijapur - shahabad Railway Line | Infrastructure Development Department | Railways with Govt. of Karnataka Participation | 840.00 | |||||
| 14 | Transport & Logistics | Dharwad - Belgaum Railway Line | Infrastructure Development Department | Railways with Govt. of Karnataka Participation | 375.00 | |||||
| 15 | Transport & Logistics | Gadag- Haveri | Infrastructure Development Department | Railways with Govt. of Karnataka Participation | 350.00 | |||||
| 16 | Transport & Logistics | Development of SH-69 (for acess to Port) | Infrastructure Development Department | PWD | 315.00 | DPR done; Procurement to start | ||||
| 17 | Transport & Logistics | F | I | Improvement to Chikkanayakanahalli-Tiptur-Hassan Road (Partly MDR and partly SH) for a length of 74.00 Km | KRDCL | KRDCL | 203.00 | BOT | Awaiting Govt approval for rebid | |
| 18 | Transport & Logistics | F | I | Improvements to Dharwad-Alnavar-Ramnagar-Anmod Road (SH-34) | KRDCL | KRDCL | 193.10 | BOT | Developer selected through bidding; Agreement to be signed. | |
| 19 | Transport & Logistics | F | I | Construction of Peripheral Ring Road around Bangalore City.. | BDA | BDA | 5000 | BOT | Bids received against RFQ; To be finalised by end May '10. | |
| 20 | Transport & Logistics | F | I | Development of Tornagallu-kudligi Road, Sandur Hospet Road | PWD | PWD | 144.00 | BOT | Bidding process to be initiated on Fin Dept approval | |
| 21 | Transport & Logistics | F | I | Improvements to Wagdhari-Ribbanapally Road | KRDCL | KRDCL | 196.53 | BOT-Annuity | Developer selected through bidding; Agreement to be signed. | |
| 22 | Transport & Logistics | F | I | Development of bypass road for Belekeri Port | PWD | PWD | 25.00 | BOT | 1. DPR completed | |
| 2. Bidding process to be initiated | ||||||||||
| 23 | Transport & Logistics | F | I | Two diversion from Bannihatti to NH-63 at BPTCL(19Km) and Bannihatti to Gadiganur(9Km) on StateHighway (SH-40) from Sandur to Torangallu, | KRDCL | KRDCL | 56.00 | BOT | IDECK has submitted DPR to GOK as part of SH-40 development on BOT basis | |
| 24 | Transport & Logistics | F | I | Improvement of Hospet-Hubli-Ankola NH-63 (271Km) | NHAI | BOT | DPR under Preparation | |||
| 25 | Transport & Logistics | F | I | Development of road Shimoga-Honnalli-Harapanahalli-Kudligi-Sandur-Thoranagal and other connecting roads. (Package 2) | KRDCL | Karnataka Road Development Corporation Limited. | 867.4 | DBOT | DPR preparation to conclude shortly | |
| 26 | Transport & Logistics | F | I | Development of road Thamilnadu border to Attibele-Sarjapur-Hoskote-Jangamakote-Shidlgatta join SH-58 and other connecting roads. ( Package 3) | KRDCL | Karnataka Road Development Corporation Limited. | 356.48 | DBOT | DPR preparation to conclude shortly | |
| 27 | Transport & Logistics | F | I | Development of road Sira-Madugiri-Gowribidanur-Chikkaballapura-Shidalgatta-Chithamani-Srinivasapur-Mulbagal (SH-58) and other connecting roads. | KRDCL | Karnataka Road Development Corporation Limited. | 1432.4 | DBOT | DPR preparation to conclude shortly | |
| ( Package 8) | ||||||||||
| 28 | Transport & Logistics | Development of road from Mysore-Bannur-Mallavali-Maddur-Huliyuru durga-Kunigal-Tumkur-Koratagere (SH-33) and other connecting roads. ( Package 13) | KRDCL | Karnataka Road Development Corporation Limited. | 627.84 | DBOT | DPR preparation to conclude shortly | |||
| 29 | Transport & Logistics | F | I | Development of road from AP border near Kothadoddi-Yaragara-Purthipalli to join SH-23 near Kapgal and other connecting roads. (Package 34) | KRDCL | Karnataka Road Development Corporation Limited. | 468.68 | DBOT | DPR preparation to conclude shortly | |
| 30 | Transport & Logistics | F | I | Development of road from Tawargere - Hulihyder-Kanakgeri-Gonal-Chikka Jantakal - Kuditheni (SH-29). (Package 35) | KRDCL | Karnataka Road Development Corporation Limited. | 585.04 | DBOT | DPR preparation to conclude shortly | |
| 31 | Transport & Logistics | F | I | Development of road from Gangavathi -NH-63 at Koppal-Mundargi and other connecting roads. (Package 38) | KRDCL | Karnataka Road Development Corporation Limited. | 721.24 | DBOT | DPR preparation to conclude shortly | |
| 32 | Transport & Logistics | Development of Airstrip at Raichur, Chikkamangalore, Gadag & Bagalkot | Infrastructure Development Department | Karnataka Housing Board | 145.45 | BOT - Annuity | DPR done; proposed for bidding under annuity mode. Land by Govt., Bid in June 2010 | |||
| 33 | Transport & Logistics | F | B | Construction of new greenfield Airport at Bellary | IDD | IDD | 140.00 | BOT | Project Development Agreement about to be signed | |
| 34 | Transport & Logistics | F | F | Development of Modern Bus Station & Commercial building on NWKRTC at Hubli Bus Stand | NWKRTC | KIPDC | 40.00 | DBOT | Rebid to be udnertaken. | |
| 35 | Transport & Logistics | F | F | Development of Modern Bus Station & Commercial Complex on NEKRTC at Gulbarga Bus Stand | NEKRTC | KIPDC | 29.60 | DBOT | Rebid to be undertaken. | |
| 36 | Transport & Logistics | F | F | Development of Modern Bus Station & Commercial Complex on KSRTC site and vacant land parcels at Puttur | KSRTC | KIPDC | 15.00 | DBOT | Rebid to be undertaken ` | |
| 37 | Transport & Logistics | F | F | Project development of Bus stand and vaccant land parcels for KSRTC at Mangalore. | KSRTC | KIPDC | 20.70 | DBOT | Restructuring and rebidding of the project soon | |
| 38 | Transport & Logistics | F | F | Project development of vacant parcels for Transport Infrastructure and Commcercial development at Hassan | KSRTC | KIPDC | 91.00 | DBOT | Re-bidding to be undertaken soon. | |
| 39 | Transport & Logistics | F | F | Project development of vacant parcels for Transport Infrastructure and Commcercial development at Chitradurga | KSRTC | KIPDC | 37.00 | DBOT | Rebidding of the project soon. | |
| 40 | Transport & Logistics | F | F | Development of Commercial Complex on NEKRTC site at Bidar | NEKRTC | KSIIDC | 28 | DBOT | Bid process to be initiated | |
| 41 | Transport & Logistics | F | F | Development of Modern Bus Station and Commercial Building on NWKTRC site at Belgaum | NWKRTC | KSIIDC | 30.00 | DBOT | Project structure made more investor friendly. Rebid to be initiated. | |
| 42 | Transport & Logistics | F | F | Traffic & TransitManagement Centre (TTMC) along with commercial development at Hebbal | BMTC | BMTC | 350 | DBOT | Re-bidding process to be initiated | |
| 43 | Transport & Logistics | Integrated traffic Hubs at Bayyappanahaly, Majestic, Bajpe | BMRCL/ KSRTC/ IDD | BMRCL/ KSRTC/ IDD | ||||||
| Note: | IDD - | IDD | Infrastructure Development Department | |||||||
| PWD | PWD | Public Works Department | ||||||||
| KSIIDC | KSIIDC | Karnataka State Industrial Investment & Development Corporation | ||||||||
| BARL | Bangalore Airport Rail Link Limited | |||||||||
| KSHIP | Karnataka State Highway Improvement Project | |||||||||
| VADA | Vijayanagar Area Development Authority | |||||||||
| KIPDC | KSIIDC & IL&FS Project Development Company | |||||||||
| KSRTC | Karnataka State Road Transport Corporation | |||||||||
| NWKRTC | North-West Karnataka Road Transport Corporation | |||||||||
| NEKRTC | North-East Karnataka Road Transport Corporation | |||||||||
| NHAI | National Highway Authority of India | |||||||||
| BUDA | Belgaum Urban Development Authority | |||||||||
| iDeCK | infrastructure Development Corporation (Karnataka) Limited | |||||||||
| BDA | Bangalore Development Authority | |||||||||
| KRDCL | Karnataka Road Development Corporation Limited | |||||||||
| PCKL | Power Corporation Karnataka Limited | |||||||||
| DMA | Directorate of Municipal Administration | |||||||||
| MCC | Mysore City Corporation | |||||||||
| GAIL | Gas Authority of India Limited | |||||||||
| KIADB | Karnataka Industrial Area Development Board | |||||||||
| BMTC | Bangalore Metropolitan Transport Corporation | |||||||||
| KBITS | Karnataka Biotechnology and Information Technology Services | |||||||||
| IT, BT, S&T | Information Technology, Bio-technology, Science&Technology Department | |||||||||